Bramley 400/132kV substation is an outdoor AIS substation with a double busbar arrangement at 400kV. The substation has various power system assets, including transformers, circuit breakers, isolators, etc., which transfer energy to our local distribution network.

You will have the opportunity to visit this 400kV transmission substation and ask the substation experts any questions during the visit.

The following information needs to be provided to the organsiser to enable security clearance before the visit.  Strict security checks will be conducted on site before the visit. The organsiers details are on the registration form. Full details will be included with the jointing instructions

Car Registration

Occupation 

Company 

Age

You must bring your safety footwear, without them you will be rejected for entry.

 

 

Energy
Power Equipment
Power Systems

2

Continuing Professional Development

This event can contribute towards your Continuing Professional Development (CPD) hours as part of the IET's CPD monitoring scheme.

Clock icon

23 Jul 2026 

10:00am - 12:00pm

Calender icon

Organiser

  • Berkshire Local Network

Speakers

Picture of speaker not available

Substation Manager

Manager - National Grid

Reasons to attend

This is a fantastic opportunity to visit one of the transmission levels 400kV substations

Location

Bramley Substation

Michens lane, Bramley
Tadley

RG26 5BJ
United Kingdom

Programme

10:00 Arrive and check-in

10:15 Introduction to safety rules

10:30 Check on PPE and ready to visit

10:45 Visiting on site

11:45 Wash-up and summary

12:00 Finish visit